Hume region
Find out about the maintenance work being done in the Hume region.
We’re busy rebuilding, repairing and resurfacing roads right across the state, including key routes across the Hume Region.
This year's road maintenance program is targeting high-traffic areas and busy freight routes, including some of the most important roads connecting communities in the north east.
We regularly inspect roads and carry out emergency repairs as needed, while more extensive works, such as road rebuilding and rehabilitation, are delivered during the warmer, drier months from September to May to ensure repairs are long-lasting.
Works underway
Hume Highway rehabilitation works, Sunday Creek
Rehabilitation works on a section of the Hume Highway at Sunday Creek, between Broadford-Wandong Road and McDonalds Road.
Crews are working on the road surface of the 1.2-kilometre stretch of road between 6am and 6 pm, from Wednesday 17 June to Wednesday 8 July 2026.
During works, lane closures are in place, with reduced speed limits to ensure the safety of crews and road users.
Please note: These dates and times are subject to change due to weather conditions.
Goulburn Valley Freeway-Hume Freeway interchange, Seymour
Transport Victoria will be undertaking sign replacement works near the Goulburn Valley Freeway-Hume Freeway interchange at Seymour in the coming weeks.
To enable work to replace the gantry signs, there will be impacts on vehicles travelling both to Wodonga and to Melbourne at different times.
On Friday 29 May 2026, there will be traffic impacts for several hours from approximately 6pm.
For the initial stage of work, a closure of the Hume Freeway ramp will require vehicles travelling from the Goulburn Valley Freeway toward Wodonga to detour via the interchange and head in the Melbourne direction, before detouring through Seymour and returning to the Hume Freeway interchange to continue toward Wodonga.
Please follow the detour signs and allow extra time.
Later that evening, the second stage of work will require a lane closure and reduced speeds for vehicles using the interchange to travel toward Melbourne.
Please follow the direction of traffic controllers on-site.
On 18 June 2026, another closure of the ramp at Seymour will be required to remove and replace the gantry sign.
From 6pm, vehicles travelling toward Wodonga will again be required to detour via the interchange and head toward Melbourne, before detouring through Seymour and returning to the Hume Freeway to continue toward Wodonga.
On 19 June 2026, from 6pm there will be a lane closure and reduced speeds for vehicles travelling toward Melbourne while the second gantry sign is replaced.
Thank you for your patience while we complete this work.
Murray Valley Highway resurfacing works, Barnawartha North
Resurfacing works on the Murray Valley Highway in Barnawartha North are underway.
Crews are working on the road surface, between Logic Boulevard and the Hume Freeway, in the City of Wodonga.
We’ll be on site between 8pm and 6am, from Sunday 24 May to Wednesday 3 June, excluding Friday and Saturday nights.
During works, single lane closures are in place, with reduced speed limits to ensure the safety of crews and road users.
On Thursday 29 May and Tuesday 2 June, the on and off ramps to the Hume Freeway will be closed at night, with a signed detour in place via Barnawartha-Howlong Road and Old Barnawartha Road, and Plunketts Road.
Please note: These dates and times are subject to change due to weather conditions.
Northern Highway resurfacing works, Wallan
Resurfacing works on the Northern Highway in Wallan are underway.
Crews are working on the road surface on the ramp from the Northern Highway to the Hume Freeway.
We’ll be on site between 7pm and 5.30am, from Sunday 24 May to Thursday 4 June, excluding Friday and Saturday nights.
During work hours, the ramp from the Northern Highway to the Hume Freeway will be closed, with detours in place via Wallan-Whittlesea Road, Epping-Kilmore Road, Merriang Road and Donnybrook Road. There will also be reduced speed limits to ensure the safety of crews and road users.
Heavy vehicles will need to detour via Wandong Road to access Hume Freeway.
Please note: These dates and times are subject to change due to weather conditions.
Goulburn Valley Highway resurfacing works, Strathmerton
Resurfacing works on the Goulburn Valley Highway in Strathmerton, are underway.
Crews are working on the road surface of the road, between Bourchiers Road and Mywee Road in the Shire of Moira.
We’ll be on site between 7am and 6pm, from Thursday 4 June to Tuesday 9 June, excluding weekends and public holidays.
During works, single lane closures are in place, with reduced speed limits to ensure the safety of crews and road users.
Please note: These dates and times are subject to change due to weather conditions.
Goulburn Valley Highway, Cathkin
Rehabilitation works on a 700 metre section of the Goulburn Valley Highway at Cathkin, between the Goulburn Valley Highway/Maroondah Highway interchange and Ridds Road, will begin in May and take approximately four weeks to complete, weather permitting.
Our crews will be working day and night, during the week and possibly on weekends to deliver the works as efficiently and safely as possible.
There will be lane closures and a 40 km/hr speed reduction in place during the works with an expected delay of five to ten minutes.
Traffic management crews will be on site to help you move through the area while we complete these important works.
Please observe changed traffic condition, plan ahead and allow extra time.
Hume Freeway rehabilitation works, Tallarook
Works will be delivered on approximately 800 metres of the Hume Freeway on the southbound lane, between the Tallarook off-ramp to the railway overpass bridge at Tallarook.
Works are scheduled to start early May and take approximately 4 weeks to complete, weather permitting.
Our crews will be on site both during the day and at night, during the week and possibly on weekends to deliver the works as efficiently and safely as possible.
There will be lane closures and a 40km/hr speed reduction in place during the works with an expected delay of five to ten minutes.
Traffic management crews will be on site to help you move through the area while we complete these important works.
Please observe changed traffic conditions, plan ahead and allow extra time.
Maintenance program 2025-26
Rehabilitation works on the following roads in the Hume region will be undertaken between now and mid-2026:
- Hume Freeway, at the Main Road and Broadford - Kilmore Road Overpass at Tallarook (520m) in Strathbogie Shire
- Midland Highway, between Mill Street and Mooroopna-Murchison Road at Mooroopna (385m) in City of Greater Shepparton
- Epping-Kilmore Road
- between Kelby Lane and South Mountain Road at Wallan (490m) in Mitchell Shire
- between Caladenia Court and Broadford-Wandong Road at Heathcote Junction (980m) in Mitchell Shire
- Wangaratta-Whitfield Road, between Peipers Lane and Mansfield-Whitfield Road at Whitfield (1.8km) in Rural City of Wangaratta
Works completed
Wangaratta-Whitfield Road
We’ve completed and rebuilt a 1.8 km section of the Wangaratta-Whitfield Road between Peiper Lane and Whitty Lane.
These works included pavement, drainage and guardrail works, along with patching and resurfacing works south of Gentle Annie Lane.
These works now provide a smoother, safer journey for all road users in the King Valley.

Images: Wangaratta-Whitfield Road
Maintenance works on the Benalla-Tatong Road/Hume Freeway Overpass at Benalla
We’ve undertaken maintenance works on the Benalla-Tatong Road/Hume Freeway Overpass at Benalla.
These works have restored the road surface and improved the drainage making the road safer for all road users.

Image: Benalla-Tatong Road / Hume Freeway Overpass
Mansfield-Woods Point Road
We’ve completed vital maintenance works on the Mansfield-Woods Point Road. These works included asphalting, sealing and linemarking.
These works now provide a smoother, safer journey for all road users.

Images : Mansfield-Woods Point Road at Woods Point
Epping-Kilmore Road, Heathcote Junction
We’ve completed rehabilitation works on both sections of the Epping-Kilmore Road between Kelby Lane and South Mountain Road, Wallan and between Caladenia Court and Broadford-Wandong Road at Heathcote Junction.
These works now provide a smoother, safer journey for all road users.
Bogong High Plains Road
We’ve delivered vital major patching and crack sealing works on the Bogong High Plains Road at Falls Creek.
These works now provide a smoother, safer journey for all road users.

Image: Bogong High Plains Road at Falls Creek
Resurfacing work will also be carried out on many roads across the Hume region as part of the 2025-26 Victorian road maintenance program:
| Road | Location and LGA |
|---|---|
| Melba Highway |
|
| Northern Highway |
|
| Hume Freeway |
|
| Omeo Highway |
|
| Murray Valley Highway |
|
| Midland Highway |
|
| Goulburn Valley Highway |
|
| Maroondah Highway |
|
| Great Alpine Road |
|
| Barmah-Shepparton Road |
|
| Benalla-Tocumwal Road |
|
| Benalla-Yarrawonga Road |
|
| Chiltern-Rutherglen Road |
|
| Murray River Road |
|
| Whittlesea-Yea Road |
|
| Heidelberg-Kinglake Road |
|
Note: We regularly inspect every single kilometre of our arterial road network. This program is subject to change based on expert inspections and in-depth technical data, ensuring that works are delivered where local drivers need them most.
Get in touch
If you have any questions about these projects, please contact DTP:
- Email: [email protected]
- Call: 133 778