Hume region
Find out about the maintenance work being done in the Hume region.
We’re busy rebuilding, repairing and resurfacing roads right across the state, including key routes across the Hume Region.
This year's road maintenance program is targeting high-traffic areas and busy freight routes, including some of the most important roads connecting communities in the north east.
We regularly inspect roads and carry out emergency repairs as needed, while more extensive works, such as road rebuilding and rehabilitation, are delivered during the warmer, drier months from September to May to ensure repairs are long-lasting.
Works underway
Murray River Road over Burrowye Creek, Burrowye
Following recent heavy rain and flooding events in north east Victoria our structures team has identified repair works required to the embankment of Burrowye Creek underneath the Murray River Road in Burrowye.
We’ve put in place a lane closure and reduced speed limit of 40km/h over Burrowye Creek bridge on the Murray River Road.
Oversize Overmass (OSOM) vehicles will not be able to travel over the bridge and will need to seek an alternative route.
We will provide further updates as works progress.
Kiewa Valley Highway maintenance works
We’ll be undertaking vital maintenance works on the Kiewa Valley Highway between Wodonga-Yackandandah Road and Lindsay Road.
The works are required to repair a damaged culvert and restore the road surface following recent heavy rain fall.
The Kiewa Valley Highway will be closed between Wodonga-Yackandandah Road and Lindsay Road from Tuesday 25 August while works are completed.
Motorists will be required to detour around the work site using Wodonga-Yackandandah Road and Linsday Road. Please follow the detour signs and allow extra time.
Works are expected to take 4 days, weather permitting. Once works start , the road closure and detour will remain in place until the works are completed.
Traffic management crews will be on site to help you move through the area while we complete these important works.
Please note: These dates and times are subject to change due to weather conditions.
Hume Freeway rehabilitation works, Sunday Creek
Rehabilitation works on a section of the Hume Freeway at Sunday Creek, between Broadford-Wandong Road and McDonalds Road, will take a break over the coming weeks, with crews expected to return during more favourable weather conditions in October.
During the works suspension reduced speed limits will be in place for the safety of road users.
Maintenance program 2025-26
Rehabilitation works on the following roads in the Hume region will be undertaken between now and mid-2026:
- Hume Freeway, at the Main Road and Broadford - Kilmore Road Overpass at Tallarook (520m) in Strathbogie Shire
- Midland Highway, between Mill Street and Mooroopna-Murchison Road at Mooroopna (385m) in City of Greater Shepparton
- Epping-Kilmore Road
- between Kelby Lane and South Mountain Road at Wallan (490m) in Mitchell Shire
- between Caladenia Court and Broadford-Wandong Road at Heathcote Junction (980m) in Mitchell Shire
- Wangaratta-Whitfield Road, between Peipers Lane and Mansfield-Whitfield Road at Whitfield (1.8km) in Rural City of Wangaratta
Works completed
Goulburn Valley Highway resurfacing works, Strathmerton
We’ve completed resurfacing works on the Goulburn Valley Highway between Bourchier Road and Mywee Road in Strathmerton.
Murray Valley Highway resurfacing works, Barnawartha
We’ve completed resurfacing works on the Murray Valley Highway in Barnawartha North, between Logic Boulevard and the Hume Freeway.
Northern Highway resurfacing works, Wallan
We’ve completed resurfacing works on the Northern Highway in Wallan from the ramp from the Northern Highway to the Hume Freeway.
Goulburn Valley Highway, Cathkin
We’ve completed rehabilitation works on a 700-metre section of the Goulburn Valley Highway at Cathkin, between the Goulburn Valley Highway/Maroondah Highway interchange and Ridds Road,
These works now provide a safer journey for all road users.
Hume Freeway rehabilitation works, Tallarook
We’ve completed works on the Hume Freeway at Tallarook on the southbound carriageway. These works were between the Tallarook off-ramp to the railway overpass bridge at Tallarook.
Wangaratta-Whitfield Road
We’ve completed and rebuilt a 1.8 km section of the Wangaratta-Whitfield Road between Peiper Lane and Whitty Lane.
These works included pavement, drainage and guardrail works, along with patching and resurfacing works south of Gentle Annie Lane.
These works now provide a smoother, safer journey for all road users in the King Valley.

Images: Wangaratta-Whitfield Road
Maintenance works on the Benalla-Tatong Road/Hume Freeway Overpass at Benalla
We’ve undertaken maintenance works on the Benalla-Tatong Road/Hume Freeway Overpass at Benalla.
These works have restored the road surface and improved the drainage making the road safer for all road users.

Image: Benalla-Tatong Road / Hume Freeway Overpass
Mansfield-Woods Point Road
We’ve completed vital maintenance works on the Mansfield-Woods Point Road. These works included asphalting, sealing and linemarking.
These works now provide a smoother, safer journey for all road users.

Images : Mansfield-Woods Point Road at Woods Point
Epping-Kilmore Road, Heathcote Junction
We’ve completed rehabilitation works on both sections of the Epping-Kilmore Road between Kelby Lane and South Mountain Road, Wallan and between Caladenia Court and Broadford-Wandong Road at Heathcote Junction.
These works now provide a smoother, safer journey for all road users.
Bogong High Plains Road
We’ve delivered vital major patching and crack sealing works on the Bogong High Plains Road at Falls Creek.
These works now provide a smoother, safer journey for all road users.

Image: Bogong High Plains Road at Falls Creek
Resurfacing work will also be carried out on many roads across the Hume region as part of the 2025-26 Victorian road maintenance program:
| Road | Location and LGA |
|---|---|
| Melba Highway |
|
| Northern Highway |
|
| Hume Freeway |
|
| Omeo Highway |
|
| Murray Valley Highway |
|
| Midland Highway |
|
| Goulburn Valley Highway |
|
| Maroondah Highway |
|
| Great Alpine Road |
|
| Barmah-Shepparton Road |
|
| Benalla-Tocumwal Road |
|
| Benalla-Yarrawonga Road |
|
| Chiltern-Rutherglen Road |
|
| Murray River Road |
|
| Whittlesea-Yea Road |
|
| Heidelberg-Kinglake Road |
|
Note: We regularly inspect every single kilometre of our arterial road network. This program is subject to change based on expert inspections and in-depth technical data, ensuring that works are delivered where local drivers need them most.