Road Maintenance

Barwon South West region

Find out about road maintenance work in the Barwon South West region.
BarwonSouthWest web page


Active work

Resurfacing works, Timboon

Resurfacing works on Timboon-Colac Road (Barrett Street), Timboon-Port Campbell Road (Main Street) and Timboon-Nullawarre Road (Bailey Street) in Timboon, are underway.

Crews are working on the surface of the road in the township of Timboon.

We’ll be on site between 6pm and 6am, from Monday 26 October to Monday 2 November 2026, excluding Friday and Saturday nights.  

During works, there will be a lane closures in place, with traffic controllers in place to allow traffic through the site, one lane at a time. There will also be reduced speed limits to ensure the safety of crews and road users. 

Please note: These dates and times are subject to change due to weather conditions.

Bayside Road (Seabeach Parade and Lowe Street) rehabilitation works, North Geelong

Rehabilitation works on Bayside Road (Seabeach Parade and Lowe Street), between Sea Breeze Parade and Refinery Jetty are almost complete.

Crews are undertaking final works between 7am and 6 pm, from Thursday 15 October to Friday 30 October 2026.  

From Thursday 15 October to Tuesday 20 October 2026, there will be single lane closures in place on Bayside Road, with temporary traffic signals in place to guide traffic through the site, one lane at a time. There will be side road closures, with signed detours and reduced speed limits in place to ensure the safety of crews and road users.  

From Wednesday 21 October to Wednesday 28 October 2026, St Georges Road will be closed between Bayside Road and the level crossing, with a detour in place via North Shore Road, Princes Highway and Bayside Road.

Final clean up and line marking works on Bayside Road and St Georges Road will follow the completion of these works on Thursday 29 and Friday 30 October 2026.  

Traffic management crews will be on site to help you move through the area while we complete these important works.

Please note: These dates and times are subject to change due to weather conditions. 

Princes Highway rehabilitation works, Panmure

Rehabilitation works on a 980m stretch of the Princes Highway in Panmure, between Ellerslie-Panmure Road and Harris Street, are underway.

Crews are working on the road surface in Moyne Shire between 7am and 6pm Monday to Friday, with the possibility of some weekend works, from 5 October 2026 for up to eight weeks.

During works, single lane closures are in place, with reduced speed limits to keep crews and road users safe.

Please note: These dates and times are subject to change due to weather conditions.

Planned work

Rehabilitation works

Rehabilitation works on the following roads in the Barwon South West region will be undertaken by mid-2027:

RoadLocationLGA
Princes Highway WestBetween Waurn Ponds Drive and Anglesea Road bridge at Waurn Ponds (870m)City of Greater Geelong
 Near Pigdons Road underpass at Fyansford (1.7km)City of Greater Geelong
 Between Barrabool Road and Thornhill Road at Highton (1.4km)City of Greater Geelong
 Near Thornhill Road at Waurn Ponds (830m)City of Greater Geelong
 Between Barrabool Road and Hamilton Highway at Fyansford (1.5km)City of Greater Geelong
 Between Waurn Ponds Drive and Thornhill Road at Waurn Ponds (890m)City of Greater Geelong
 Between Anakie Road bridge and Cowies Creek at Bell Post Hill (1.1km)City of Greater Geelong
 Between Creamery Road and Midland Highway at Bell Post Hill (1.1km)City of Greater Geelong
 Between Illowa Road and Fitzgibbons Lane at Illowa (740m)Moyne Shire
Hamilton HighwayBetween Nagorckas Road and Picnic Road at Tarrington (2.6km)Southern Grampians Shire
Ayresford RoadNear Baxters Road at Dixie (1.3km)Corangamite Shire
Geelong-Bacchus Marsh RoadBetween Peak School Road and Carrs Road at Anakie (950m)City of Greater Geelong
Coleraine-Edenhope RoadBetween Coleraine-Balmoral Road and Lyons Lane at Coleraine (4.4km)Southern Grampians Shire
Foxhow RoadBetween Bakers Lane and Robertson Street at Foxhow (1.7km)Corangamite Shire
 Between Leslie Manor Road and Howells Road at Leslie Manor (4.9km)Corangamite Shire
Warrnambool-Caramut RoadBetween Russells Road and Sims Road at Winslow (1km)Moyne Shire
Spencer RoadBetween Sommervilles Road and Toolong North Road at Kirkstall (1.8km)Moyne Shire
Deans Marsh-Lorne RoadNear Pennyroyal Station Road at Deans Marsh (1.6km)Surf Coast Shire
Camperdown-Lismore RoadBetween Lower Darlington Road and Lake Tooliorook Road at Lismore (2.9km)Corangamite Shire

 

Resurfacing works

Resurfacing work will also be carried out on many roads across the Barwon South West region:

RoadLocationsLGA (number of jobs)
Princes Highway West

Corio, Fyansford, Lovely Banks, Waurn Ponds

Winchelsea, Buckley, Mount Moriac

Warncoort, Pomborneit

City of Greater Geelong (5)

Surf Coast Shire (7)

Colac Otway Shire (2)

Hamilton Highway

Lismore, Derrinallum

Mortlake

Corangamite Shire (3)

Moyne Shire (1)

Anglesea RoadFreshwater CreekSurf Coast Shire (1)
Barwon Heads RoadConnewarreCity of Greater Geelong (4)
Lower Duneed RoadMount Duneed, Armstrong CreekCity of Greater Geelong (2)
Winchelsea-Deans Marsh RoadWinchelsea SouthSurf Coast Shire (1)
Geelong-Ballan RoadMoorabool, AnakieCity of Greater Geelong (3)
Foxhow RoadKariah, Leslie ManorCorangamite Shire (2)
Mt Duneed RoadMount DuneedCity of Greater Geelong (2)
Forest RoadCorio, LaraCity of Greater Geelong (4)
Mortlake-Ararat RoadWoorndooMoyne Shire (1)
Timboon-Colac RoadTimboonCorangamite Shire (1)
Timboon-Port Campbell RoadTimboonCorangamite Shire (1)
Timboon-Nullawarre RoadTimboonCorangamite Shire (1)
Darlington RoadBookaarCorangamite Shire (1)

 

Gallery

Bayside Rd BSW newsletter SeptemberRehabilitation works underway on Bayside Road in North Geelong
DTP 02 Geelong Ring Road_Night_DJI_20260612012635_0482_D (1)Rehabilitation works underway on Geelong Ring Road at Fyansford
Terang-Mortlake Road rehabRehabilitation works underway on Terang-Mortlake Road.
Terang-Mortlake Road rehab2Rehabilitation works underway on Terang-Mortlake Road.

Get in touch

If you have any questions about these projects, please contact Transport Victoria:

Email: [email protected]