We’re delivering vital maintenance on Frankston-Flinders Road in Balnarring to provide a smoother, safer journey for all road users.

Project status:

Underway


Update – June 2026

We’re working during the day under a road closure between 7am and 4pm from Tuesday 23 June to Sunday 5 July 2026 (with the possibility of some weekend works). Dates and times are subject to change due to weather conditions.

We need to complete these works during the day as works to restore the final layer of pavement (wearing course) can no longer be completed at night due to overnight cold temperatures that prevent the asphalt from setting.

After the completion of asphalt works, the line marking works will be carried out at night.

What to expect during works

  • A daily road closure on Frankston-Flinders Road between Sandy Point Road and Coolart Road with detours will in place.
  • A detour will be in place via Balnarring Road, Bittern-Dromana Road and Coolart Road.
  • Crews will work with property owners to maintain access to private properties and businesses within this section of Frankston-Flinders Road.
  • No parking on this section of Frankston-Flinders Road.
  • Medium to high levels of noise when crews remove the surface layers of road. Low to medium levels of noise are expected during all other works.
  • Crews use modern equipment to keep noise to a minimum, however the works will unavoidably emit some noise and light. For the safety of road users and workers, reversing beepers are required on all machinery.
  • Emergency service vehicle access will be maintained.
  • A reduced speed limit around the work site to ensure the safety of crews and all road users.


This project is part of the 2025-26 road maintenance program.

Detour map

Image of map showing detour route during the maintenance works at the Frankston-Flinders Road at Balnarring

Click to enlarge map 

What we’re doing

We’re delivering vital maintenance works on approximately 2.1 kilometres of Frankston-Flinders Road between Sandy Point Road and Coolart Road.

The works will involve replacing layers of the road, asphalt resurfacing and line marking to restore the condition of the road surface.

Get in touch

Find out more about the Victorian 2025-26 road maintenance program here.

Email:  [email protected]

Call:     133 778